April 14, 2008: Construction Update for Aberdeen Energy

  • There are 360 workers on-site (working 7 days a week, 12 hours a day.
  • We are still on track for a May 2008 startup.
  • Process Building - Piping, insulation, electrical continues. 
  • Rail load out – pipe rack is about 75% complete.
  • Energy Center – about 90% completed
  • The plant overall is looking good
  • Grains –started doing some of their electrical checkout; bumping motors, etc…
  • Start-up team to be on-site the last week in April.
  • Permanent power has been energized
  • finishing phase II work
  • Rail –still on track to be completed in April.    
  • Truck Scale House and Grains office building – The scale house; is enclosed with doors, windows, house wrap, and steel siding.  Wiring is roughed in, sheet rock is complete, cabinet’s installed, HVAC almost complete; should run the main power today.  The grains office footings and walls are poured and backfilled; depending on the weather the slab floor will be poured early this week

April 2, 2008: Aberdeen Energy

Scale House
Scale House
Scale House
Fire water tank and rail load out pipe rack
April 10: Cooling tower piping east of Energy Center

 

March 18, 2008: Aberdeen Energy

Evap and distillation
East side of energy center looking towards cooling tower
Cook Alley

February 28, 2008 - Aberdeen Energy Construction

Hoop tent storage building
Footings for west wall of wet cake pad
Energy Center roofing being installed above dryer A and B
Distillation columns
B&B installing the wet well
B&B crew installing force main
installing flour conveyor from hammer mills

Aberdeen Energy Construction Update (2/29/08)
We are still on track for a May 2008 start up in lieu of the severe cold weather we have had this year. Fagen, Inc our builder continues to work 7 days week and we have a total of 270 workers on site to date. The Process Building is 98% enclosed with steel siding. The wetcake pad is under construction. The Energy Center is 60% complete and R&R Contracting has about 75% of the rail loop complete with a final completion date of mid March. Piping in Process and Fermentation areas continues. Fagen has began insulating process tanks and piping and  B&B Contracting are installing the force main and wet well for the plant effluent water discharge. GLE has been sponsoring a monthly cookout with the most recent one on February 13 for the construction employees. These cookouts are much appreciated with the cold weather. The cooling tower is almost complete with the exception of pumps and piping. Dry wall is installed in the offices, lab, control, etc in the process building.

 

February 22, 2008 - Aberdeen Energy construction

Mole sieve platforms being installed
Energy Center conveyors
Biomethanator being insulated

February 14, 2008 - Aberdeen Energy construction

Looking NW from 370 Avenue
Looking north from 370th Ave.
Looking NE from 370th Ave.
Process building SW corner
Rail work west of grains receiving building
Bio methanator tanks being insulated
Grains receiving
Ease end of Process looking at maintenance doors
Wet cake pad wall
Energy Center
Centrate tank and piping
     
Energy Center-DDG cooling drum
     

 

February 6, 2008 - Construction at Aberdeen Energy

Water treatment building
TO stack set in place
Southwest side of Energy Center
South MCC Energy Center
Looking at east side of Process Building outside maintenance area
Footings for wetcake pad
East side of Process Building


January 30, 2008 - Construction continues at Aberdeen Energy. . .

View of plant looking SE from Hwy 12
TO stack being insulated
Tank farm looking SE from Hwy 12
Process building NW corner and liq tank insulated
Process building NE corner
Process area SE corner
Looking at south end of process building
Looking at natural gas south of admin building
Looking at cook water meth feed and thin stillage tank pumps
Inside grains receiving building
Hammer mills south side Bliss brand 300 hp
Hammer mills north side Bliss brand 300 hp
Grains receiving looking SE
Fermentation north end
Fermentation looking south east
Energy center MCC south
Energy center NW corner
Ferm tank repair piece and siding between ferms
View of plant looking south east
Energy center MCC north

 

January 3, 2008 - Contruction at Aberdeen Energy

CO2 Scrubber
Cook Alley
Cooling Tower
Energy Center
south east corner
Energy Center
south west corner
Evaps and mole sieves
Grains
Grains
Process building looking south west

 


See groundbreaking photos for Aberdeen Energy and Missouri Valley Energy, LLC!

03-5-08 - Minnesota Moves Towards E20 Mandate Read More...

12-19-07 - President Signs Historic Renewable Fuels Standard Calling for 36 Billion Gallons of Ethanol Use Read More...

12-18-07 - GLE Expansion Complete Read More...

Setting the Record Straight on GLE- Read More. . .

Granite Falls Energy, LLC Annual Meeting Article

News Story 1/8/07 Glacial Lakes pulling out of Granite Falls Energy venture Read More. . .

 