From a dream to reality. . . 2002
- January 2002 - Process
piping begins
- February 2002 - The
Administration Building is completed and GLE staff relocates to new
offices
- March 2002 - McCormick
Construction begins slipping concrete grain silos
- March 2002 - Box culverts
installed at water crossings for railroad spur.
- April 2002 - Thermo-Oxidizer
150 foot exhaust stack is set
- May 2002 - Centrifuges
are set in Energy Center
- June 2002 - GLE operating
team comes on board
- July 2002 - Control
System comes on line
- July 2002 - Grain
Receiving and storage area becomes ready for operation As of July
2002, construction continues with an expected start date of September
1, 2002.
- August 2002 - Ribbon
Cutting & Grand Opening ceremonies held with over 2000 people
in attendance
- August 2002 - Cook & fermentation
area started using water as a simulator
- August 21, 2002 -
Grain Receiving begins accepting corn
- August 25, 2002 -
Began Grinding Corn
- August 28, 2002 -
First DDG produced at GLE
- August 28, 2002 -
First 190 Proof Ethanol Produced at GLE
- September 11, 2002 -
First railcar of ethanol shipped
- October 2, 2002 -
GLE First Jumbo Car filled with 104 ton of DDG
- November 2002- Improvements are made to Grain
Receiving Area
- November 2002- Fagen, Inc. completes project
and moves off site
- December 2002- 30” diameter stainless
steel duct is added to south side of concrete silos to dissipate
any odors that might exhaust from the DDG building
- December 2002-Flare is installed to burn off
odors from rail car and truck load out
- December 2002- GLE holds its First
Employee Appreciation Christmas Party
- December 2002- GLE is running at above nameplate
capacity
|
|